Auburndale Technology Center

On November 4, 2026, the City of Auburndale received a permit application from Hillwood Development to retrofit an existing warehouse into a data center, known as the Auburndale Technology Center. The proposed project involves converting an existing industrial facility to accommodate data center operations. The application is subject to the City’s established permitting and development review processes, including compliance with applicable local, state, and federal regulations.

The City of Auburndale is committed to transparency and ensuring that residents have access to accurate, timely, and factual information regarding developments within our community. As part of this commitment, the City has established this webpage to serve as a centralized resource for information, project documents, and updates related to the proposed Auburndale Technology Center.

The City will provide access to all project-related information legally permissible for public disclosure, in accordance with applicable public records laws. The documents available below represent the materials currently available to the City and are provided to help residents better understand the proposed development and the associated review process.

As the permitting and review process progresses, this webpage will be updated to reflect additional documents and other information as it becomes available.

Project Documents

The following documents have been made available for public review. Additional materials will be added as they become available and are eligible for public disclosure.

This Page Last Updated: November 20, 2026 | 2:08 P.M.

Frequently Asked Questions

Please note: Responses to some questions are still being prepared and will be provided as they become available.

HILLWOOD

The developer is supplying documentation on water consumption/potable water and a 24-hour decibel study as well as low frequency noise information for the public. 

TECO

ADMINISTRATIVE

Land Development Regulations: Sec. 5.3.15. ADMINISTRATION AND ENFORCEMENT – WHEN DETERMINATION OF VIOLATION REQUIRES HIGHLY SKILLED PERSONNEL AND EXPENSIVE INSTRUMENTS.  

Where determination of violation of performance standards entails the use of highly skilled personnel and expensive instrumentation not ordinarily available to the City, and when, in the considered judgment of the Administrative Official a violation exists, procedure shall be as follows:  

5.3.15.1. NOTICE. The Administrative Official shall give written notice, by certified mail, return receipt requested, or other means insuring a signed receipt for such notice, to those responsible for the alleged violation.  Such notice shall describe the particulars of the alleged violation and the reasons why the Administrative Official believes there is a violation in fact, and shall require an answer or a correction of the alleged violation to the satisfaction of the Administrative Official within a reasonable time limit set by the Administrative Official but in no case more than 10 days.  The notice shall state, and it is hereby declared, that failure to reply or to correct the alleged violation to the satisfaction of the Administrative Official within the time limit set constitutes admission of violation.  The notice shall further state that upon request of those to whom it is directed, technical determinations as described in the appropriate portions of this Chapter will be made; and that if violation as alleged is found, costs of the determinations shall be charged against those responsible, in addition to such other penalties as may be appropriate; and that if it is determined that no violation exists, costs of the determinations will be paid by the City. 

5.3.15.2. CORRECTION OF VIOLATION WITHIN TIME LIMIT. If, within the time limit set, there is no reply but the alleged violation is corrected to the satisfaction of the Administrative Official, he shall note “Violation Corrected” on his copy of the notice and shall retain it as part of his records, taking such other action as may be warranted by the circumstances of the case. 

5.3.15.3. NO CORRECTION; NO REPLY. If there is no reply within the time limit set, thus establishing admission of violation as provided in Subsection 5.3.15.1. above, and the alleged violation is not corrected to the satisfaction of the Administrative Official within the time limit set, he shall take or cause to be taken such action as warranted by continuation of an admitted violation after notice to cease. 

Land Development Regulations, Chapter 24: Violations, Penalties:  

Sec. 24.1.1. GENERAL. 24.1.1.1. Violation of the provisions of the Land Development Regulations or failure to comply with any of the requirements contained therein, including violations of conditions and safeguards established in connection with grants of variances or special exceptions, shall constitute a misdemeanor. 24.1.1.2. The owner or tenant of any building, structure, premises or part thereof, any architect, builder, contractor, agent or other person who commits, participates in, assists in or maintains such violation may each be found guilty of a separate offense and suffer the penalties herein provided. 24.1.1.3. It shall be a misdemeanor for any person to destroy, move, remove, deface or obscure any sign or notice erected or posted pursuant to the requirements of the Land Development Regulations. 24.1.1.4. Nothing contained herein shall prevent the City from taking any other lawful action necessary to prevent or remedy any violation. 

Sec. 24.2.1. GENERAL. 24.2.1.1. Any person who violates the provisions of the Land Development Regulations or fails to comply with any of its requirements, shall upon conviction thereof, be fined not more than $500 or imprisoned for not more than 60 days, or both, and in addition shall pay all costs and expenses involved in the case.  Each day such violation continues shall be considered a separate offense. 

A moratorium will be presented to City Commission on December 21, 2026, for future data center development. The Auburndale Technology Center project would not be included in this moratorium.

If the permits do not meet the Florida Building Code, Fire Code Florida Statutes, or Land Development Regulations then any permit can be denied. 

An outside consultant engineer is being retained by the City for permit and document review. 

This would be dependent on the City Building Official, Utilities and any outside agencies which require compliance with operation numbers. The City will be monitoring the project post construction including noise profile by acoustical engineer. 

Bonds are not required with permits. TECO and the developer have a cost agreement for infrastructure. 

Not unless the City’s Land Development Regulations are amended. However, Florida Senate Bill 180 (2025) (see attached link) places restrictions on the ability of affected counties and municipalities to make certain regulatory changes. Specifically, the legislation prohibits construction moratoriums, more restrictive or burdensome amendments to comprehensive plans or land development regulations, and more restrictive development review or permitting procedures.

These restrictions generally apply for one year following a hurricane’s landfall in federally declared disaster counties located wholly or partially within 100 miles of the hurricane’s track, including municipalities within those counties. Additionally, the legislation establishes restrictions associated with Hurricanes Debby, Helene, and Milton that apply retroactively to August 1, 2024, and remain in effect until October 1, 2027, subject to certain statutory exceptions.

ECONOMIC DEVELOPMENT

The applicant has indicated the project would pay approximately $14 million dollars in ad valorem taxes. Approximately $14 million in franchise fees and another $14 million in utility taxes. The city staff has asked for the study producing those numbers. The City will not consider the application review complete until the study is received and reviewed by staff and consultant. The allocation of those funds would be discussed by the City Commission during the budget process in the future.  

The economic impact will provide the possibility of reducing taxes or offsetting funding public infrastructure.

The City does not regulate job count for any industry.

The City does not regulate job retention or sources for any industry. 

ENVIRONMENTAL

Guidelines must be followed from the Department of Environmental Protection. This agency has their own regulatory system and penalty system in place. 

The City has not conducted independent studies regarding residents living near data centers.

INFRASTRUCTURE

The property at 810 Pace Road will utilize reclaimed water for irrigation purposes. The developer has inquired about reclaim availability for industrial purposes, however the reclaim water system in that area does not have the capacity to supply on a 24-hour basis at this time. There are Capital improvement projects underway at the wastewater plants that will improve the availability in the future. Upon completion of the projects, it would be recommended to the property owner to convert the industrial uses to reclaim rather than potable water supplies. 

A modification to the City of Auburndale’s water use permit (WUP) will be required per the Southwest Florida Water Management District (SWFWMD) policies adopted December 17, 2025. In discussion with SWFWMD staff, this will require a hearing before the SWFWMD board for approval. 

The project will be utilizing the City’s water system. No groundwater will be used for the project.

NOISE

The City is in the process of hiring an Acoustical Engineer to review the sound study being conducted by Hillwood. Staff has asked Hillwood to address the low frequency sound profile. The acoustical engineer will be asked to ensure mitigation proposed for low frequency sound is adequate.  Post construction sound study will also be completed to determine if the levels are consistent with the original study.   

The City will require Hillwood institute measures to mitigate any sounds above the approved sound study.

Project Documents

The following project documents were requested and pending arrival:

> Hillwood

  1. A 24-hour decibel sound study for the data center.
  2. Engineering report or document from engineer stating the consumptive use/potable water.
  3. Development Agreements between TECO and Hillwood (Draft if final documents are not complete).
  4. Contracts for monthly bills or payments to be given by Hillwood.
  5. Correspondence or agreements between the Hillwood and TECO regarding electrical load capacity, substation upgrades, or Florida Senate Bill 484 compliance.
  6. Modeling of Low Frequency Noises.